Q no 1 Load factor for heavy industries may be taken as
a ) 10 to 20%
b ) 25 to 40 %
c) 50 to 70 %
d ) 70 to 80 %
explanation
answer d ) 70 to 80 %
Q no 2. Load factor of domestic load is usually
a ) 10 to 15%
b ) 25 to 40 %
c) 50 to 70 %
d ) 70 to 80 %
explanation
answer a ) 10 to 15%
Q no 3. Depreciation charges are high in case of
a ) thermal plant
b ) diesel plant
c ) hydroelectric plant
explanation
answer a ) thermal plant